Location: Castilian Street, Northampton, NN1 1JX
Type of property: Victorian terrace constructed of 9-inch brickwork with a physical damp proof course
Services used:
Materials Used:
Problem: The basement was of brick wall construction with a solid floor; the walls had been fitted with an 8 mm mesh drainage membrane with render over, and the floor finished with bonded vinyl and bonded carpet preventing full inspection. The rest of the inspection revealed evidence of groundwater ingress at the wall/floor junction in the basement, resulting in salting to the wall plaster and wet rot to the skirtings. During periods of heavy rain, water ingress resulted in wetting of the floor. The existing installed system of waterproofing was doomed to fail due to:
Works completed: We recommended installing a full Cavity Drain Membrane System compliant with BS8102 and BS8500. We: We also advised the client to instruct a drainage survey to investigate whether the sewage system was venting directly under the floor slab